COMMITMENTS AND CONTINGENCIES
Commitments
The Company has contractual obligations and commitments primarily with regard to future purchases of aircraft, repayment of debt (see Note 6), and lease arrangements (see Note 7). During the year ended December 31, 2025, the Company entered into supplemental agreements with Boeing relating to its contractual order book for -7 and -8 aircraft. The Company's contractual order book with Boeing for -7 and -8 aircraft, which extends to 2031, was designed to support the Company's growth and fleet modernization plans, while also providing significant flexibility and optionality to manage its fleet gauge and size, including opportunities to accelerate fleet modernization efforts if growth opportunities do not materialize. The Company received 55 -8 aircraft deliveries from Boeing in 2025 and retired 48 -700 aircraft and seven -800 aircraft, including the sale of five -800 aircraft. During fourth quarter 2025, the Company exercised six -7 options for delivery in 2027, converted one 2025 -7 firm order into a 2025 -8 firm order, and converted 12 2026 -7 firm orders into 2026 -8 firm orders.
Boeing continues to experience delays in fulfilling its commitments with regards to delivery of MAX aircraft to the Company and delays in achieving FAA certification of one of its new aircraft types, the -7, for which Southwest expects to be the launch customer. During 2025, as a result of Boeing's ongoing delivery delays, the Company conservatively re-planned its capacity and delivery expectations for 2026. The Company will continue to closely monitor the ongoing aircraft delivery delays with Boeing and adjust expectations as needed.
Based on the Company's current agreement with Boeing, capital commitments associated with its firm orders as of December 31, 2025 were:
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| (in billions) | 2026 | | 2027 | 2028 | 2029 | 2030 | 2031 | Total |
| Payments for capital commitments | $ | 4.2 | | (a) | $ | 2.7 | | $ | 2.7 | | $ | 2.5 | | $ | 1.5 | | $ | 1.2 | | $ | 14.8 | |
(a) Capital commitments associated with the Company's firm orders in 2026 of $4.2 billion include approximately $2.5 billion primarily related to the existing scheduled 86 MAX aircraft to be delivered in 2026 and $1.7 billion related to 81 MAX aircraft (27 -7s and 54 -8s) that were contractually committed for 2024 and 2025, but were not received.
In addition, subsequent to December 31, 2025, and through February 5, 2026, the Company exercised four -7 options for delivery in 2027, resulting in an increase of the Company's 2027 capital commitments to $2.8 billion.
Los Angeles International Airport
In April 2023, the Company executed a lease agreement with Los Angeles World Airports ("LAWA"), which owns and operates Los Angeles International Airport ("LAX"), for the ground lease and construction of a new concourse. In this agreement, the Company will manage the development, design, financing, and construction of nine new gates, along with additional features, at LAX. Construction of the concourse is estimated to not exceed $2.3 billion. During 2024, the Company's leadership met with LAWA and agreed to pause the project, with plans to restart it in 2026. The Company expects to commence construction in 2028 with construction to be completed in 2032.
Funding for this project will flow through a credit facility and the outstanding loans are expected to be paid off directly by LAWA to the credit facility at project completion, thus reimbursing the Company on all costs drawn on the credit facility. As of December 31, 2025, the credit facility has yet to be put into place and is expected to be established closer to the beginning of construction in 2028. The Company is expected to be reimbursed by the credit facility on prior payments made once in place.
Based on this agreement, the Company has determined that it does have control over the assets during this project for accounting purposes. As a result, the costs incurred to fund this project thus far, which totaled $88 million as of December 31, 2025, are included within Assets constructed for others on the accompanying Consolidated Balance Sheet.
William P. Hobby Airport
In March 2022, the Company executed a Memorandum of Agreement ("MOA") with the City of Houston, Texas (the "City") which owns William P. Hobby Airport ("Hobby") that is managed and operated by the City's Houston Airport System. Under the MOA, the Company will manage the development, design, and construction of seven new gates in Hobby's West Concourse.
The project is currently estimated to be completed in 2027 at a cost of at least $470 million. The Company is providing initial funding for the majority of the project, but is being reimbursed for such funding from the City on a monthly basis and therefore the project has not and is not expected to significantly impact the Company’s liquidity. The City plans to fund these reimbursements utilizing rates and charges collected from current and future Hobby occupants, including the Company.
Based on the MOA, as well as an amendment to the terminal lease agreement signed in August 2023, the Company has determined that it does not control the assets during the construction period for accounting purposes, and thus is recording the amounts funded for the project as a receivable until reimbursed by the City, at which time the balance is derecognized. A balance of $88 million was reflected within Accounts and other receivables in the accompanying Consolidated Balance Sheet as of December 31, 2025.
Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business and records a liability for such claims when it is probable that a loss will be incurred and the amount is reasonably estimable.
The Company is a defendant in class action litigation asserting it has not provided paid short-term military leave to certain Employees, in violation of the federal Uniformed Services Employment and Reemployment Rights Act (“USERRA”). The United States District Court for the Northern District of California previously issued an order to
effectively stay the action, pending an appeal from an order by the United States District Court for the Eastern District of Washington granting summary judgment in favor of an airline in a separate case involving substantially the same claims at issue in this action. On February 1, 2023, the Ninth Circuit reversed the district court’s grant of summary judgment and remanded the separate airline case to the District Court. The Ninth Circuit’s decision may adversely affect the Company’s defenses in the USERRA proceeding and may give rise to additional litigation in this or other areas. On October 29, 2024, the Company filed a motion to decertify the class. On February 13, 2025, the parties filed a notice of settlement advising the Court that they reached a settlement in principle, and the parties made a stipulated request for the Court to vacate the case schedule, including the hearing on the Company's decertification motion, and to set a deadline of June 19, 2025, for the filing of either a motion for preliminary approval of the class settlement or a status update about the timing of the remaining steps in the settlement process. The Court granted the stipulation on February 14, 2025. On June 20, 2025, the Court granted the parties’ stipulated request to continue the deadline for filing a motion for preliminary approval of the class settlement. On September 25, 2025, plaintiffs filed a motion for preliminary approval of the settlement class. The settlement includes an $18.5 million settlement fund and prospective relief that includes a differential pay benefit for up to 10 days of military leave per year, which will remain in place for at least five years once initiated. On December 11, 2025, the Court granted preliminary approval of the settlement and set the final approval hearing for May 14, 2026. The proposed settlement is fully accrued as of December 31, 2025.
On December 27, 2019, a former Customer Service Agent at Oakland International Airport, filed a putative class action complaint in the Superior Court of California, for the County of Santa Clara, against the Company alleging the following seven claims under the California Labor Code and Business & Professions Code: (1) failure to provide meal periods; (2) failure to provide rest periods; (3) failure to pay hourly wages; (4) failure to provide accurate wage statements; (5) failure to timely pay all final wages; (6) unfair competition; and (7) civil penalties for the foregoing. Plaintiff filed a First Amended Complaint on October 15, 2021, that asserted the same causes of action and added a named plaintiff. The First Amended Complaint primarily seeks unpaid wages, interest thereon, and associated civil and statutory penalties, along with attorneys’ fees and costs. On February 26, 2025, the Court granted class certification as to the first cause of action for failure to provide meal periods, denied certification on the second through fourth causes of action, and granted certification on the fifth and sixth causes of action only insofar as they are predicated on the first cause of action. The certified class consists of all of the Company’s non-exempt ground Employees in California who worked a shift in excess of five hours for the time period between October 24, 2014, forward. On April 17, 2025, the Company filed a summary judgment motion arguing that Plaintiffs’ first cause of action, and all causes of action predicated thereon, failed as a matter of law. The motion was granted on July 25, 2025. Judgment was entered in favor of the Company on September 2, 2025, and Plaintiffs filed a notice of appeal on September 4, 2025. The Company is currently not able to estimate a range of possible loss with regards to the litigation to which it is a defendant.