19. Commitments and Contingencies:
(a) The Company has several non-cancelable lease and purchase obligations primarily for general office facilities, service contracts for mobile telephone services and equipment that expire over the next years. Future minimum payments under these agreements are as follows (Dollar amounts in thousands of US dollars):
| Contractual Obligations for the year ending December 31, | Contractual Lease Obligations | Debt Obligations | Capital Purchase Obligations | Redeemable preferred units financing Obligations | Notes Payable financing Obligations | Purchase Obligations (1)(2) | Total Obligations | |||||||||||||||||||||
| 2025 | $ | 7,225 | $ | - | $ | 1,885 | $ | 18,639 | $ | - | $ | 20,334 | $ | 48,082 | ||||||||||||||
| 2026 | 5,429 | 195,400 | - | 18,536 | - | 2,190 | 221,555 | |||||||||||||||||||||
| 2027 | 3,880 | - | - | 18,639 | - | 746 | 23,264 | |||||||||||||||||||||
| 2028 | 3,097 | - | - | 135,474 | 238,505 | 441 | 377,517 | |||||||||||||||||||||
| 2029 | 3,026 | - | - | - | 63,000 | 367 | 66,393 | |||||||||||||||||||||
| Thereafter | 32,669 | - | - | - | - | 1,851 | 34,520 | |||||||||||||||||||||
| $ | 55,326 | $ | 195,400 | $ | 1,885 | $ | 191,288 | $ | 301,505 | $ | 25,928 | $ | 771,331 | |||||||||||||||
| (1) Purchase obligations include all other legally binding service contracts for mobile telephone services and other operational agreements to be delivered during Fiscal 2025 and subsequent years. (2) Purchase obligations include minimum revenue commitments of $18.5 million with the Company's MNO partner between 2025 and 2026. |
(b) On February 9, 2015 Ting Fiber, Inc.(“Ting”) entered into a lease and network operation agreement with the City of Westminster, Maryland (the “City”) relating to the deployment of a new fiber network throughout the Westminster area (“WFN”).
Under the agreement, the City will finance, construct, and maintain the WFN which will be leased to Ting for a period of ten years. The network will be constructed in phases, the scope and timing of which shall be determined by the City, in cooperation with Ting.
Under the terms of the agreement, Ting may be required to advance funds to the City in the event of a quarterly shortfall between the City’s revenue from leasing the network to Ting and the City’s debt service requirements relating to financing of the network. Ting could be responsible for shortfalls between $50,000 and $150,000 per quarter. In Fiscal 2016, the City has entered into financing for the construction of the WFN which allows the City to draw up to $21.0 million from their lenders over the next years with interest only payments during that period with a loan maturity of 30 years. As of December 31, 2024, the City has drawn $16.2 million and the City’s revenues from Ting exceed the City’s debt service requirements. The Company does not believe it will be responsible for any shortfall in Fiscal 2025.
(c) On September 17, 2018 Ting entered into a non-exclusive access and use agreement with SiFi Networks Fullerton, LLC (“SiFi”). The agreement established a fifteen-year term during which Ting has the non-exclusive right to act as an Internet service provider for a fiber-optic network to be constructed in the city of Fullerton, California. Under the terms of the agreement, SiFi is fully responsible for constructing, operating and maintaining a wholesale fiber-optic network, as well as the financing of those activities.
Ting is responsible for paying a fee per subscriber to SiFi. Through a “take or pay” arrangement, Ting has agreed to certain minimum charges based on minimum subscriber rates. These minimum fees are variable based on the percentage completion of the fiber optic network, and thus have not been considered an unconditional purchase obligation for the purposes of the table in Note 19 (a). Ting is currently disputing certain charges from SiFi and has ceased accruing for these amounts, as it believes payment is unlikely. The commitment amounts disclosed in the schedule reflect only the charges that Ting continues to accrue. Given the ongoing dispute, these amounts may be subject to change.
(d) On November 4, 2019 Ting entered into an access and use agreement with Netly, LLC (“Netly”). The agreement establishes twelve-year term wherein Ting will be granted the right to act as an Internet service provider for fiber-optic networks to be constructed in and around the cities of Solana Beach, California. Under the terms of the agreement, Ting will have a 3-year “Headstart” period over each completed segment of the network, whereby Ting shall be the exclusive provider of services to subscribers during the “Headstart” period. Netly is fully responsible for constructing, operating and maintaining a wholesale fiber optic network, as well as the financing of those activities.
Ting is responsible for paying a fee per subscriber to Netly, as well as an unlit door fee for each serviceable address not subscribed. Through a “take or pay” arrangement, Ting has agreed to certain minimum charges based on minimum subscriber rates. To the extent that construction of the fiber optic network is complete, our minimum commitments have been included in the contractual lease obligations of the table in Note 19 (a). The Company has an ongoing billing dispute with Netly regarding the rates and methodology under which it can invoice our Ting Fiber division for our operations. For the purposes of calculating the table in Note 19 (a), the Company reflected its future commitment under this agreement consistent with the amounts it has historically accrued in accordance with ASC 450-20 and, in accordance with the definition of probable loss described therein, and paid. At this time the Company believes that the probability that this dispute will have a material adverse effect on the business, operating results or financial condition is remote.
(e) On January 7, 2022, Ting Fiber, Inc., entered into a 25-year lease agreement with Colorado Springs Utilities (“CSU”), a municipally owned utility. The lease agreement named Ting Fiber the anchor tenant on a city-wide fiber network that is intended to pass 200,000 homes in Colorado Springs, Colorado. CSU began construction in Q2 of 2023. The lease obligates Ting, and its ultimate parent Tucows, Inc., to pay a per month fee for addresses passed by the network (as they are passed and become serviceable for customers to connect to the network) and for certain fiber infrastructure, including co-location space. Total costs of the lease, over its -year term, are approximately $593,000,000 based on a fully completed fiber-to-the-home network, however the minimum fees are variable based on the percentage completion of the fiber optic network. Future committed fees associated with completed portions of the network have been included in the contractual lease obligations of the table in Note 19(a). Future fees associated with portions of the network that have yet to be constructed have not been considered an unconditional purchase obligation for the purposes of the table in Note 19(a).
(f) On May 11, 2022, Ting Fiber, LLC, entered into a "Rights-of-Way" agreement with the City of Alexandria, Virginia whereby the City granted Ting Fiber the right to install, place, construct, maintain, operate, upgrade, repair, and replace a Communications System to provide Broadband Services within the Public Rights-of-Way (a space in, upon, above, along, across, over and below the public and City-owned property that is used as a public rights-of-way) for a fee. Per the agreement, Ting Fiber is to pay the City throughout the 20-year term of the agreement, an amount equal to 3% of Ting Fiber's Broadband Revenues once the network is live, and subscribers are obtained, and this fee is to be paid on a quarterly basis. The agreement commenced once Ting Fiber launched its network in Alexandria in March 2023. Since these fees are currently variable in nature, they have not been considered an unconditional purchase obligation for the purposes of the table in Note 19(a).
(g) On November 1, 2023, the Company, entered into a Network Access and Use Agreement with Blue Suede Networks, LLC, which granted Ting Fiber the right to use the fiber communications network to be constructed by Blue Suede Networks, LLC to provide high-speed broadband Internet Access services to end-user residential and small and medium sized business customers in the city of Memphis, Tennessee. The agreement grants the Company an exclusivity period of 5 years. The agreement requires the Company to pay the greater of a minimum revenue commitment based on minimum subscriber rates and a revenue share. Future fees associated with portions of the network have not been considered an unconditional purchase obligation for the purposes of the table in Note 19(a).
(h) In the normal course of its operations, the Company becomes involved in various legal claims and lawsuits. The Company intends to vigorously defend these claims. While the final outcome with respect to any actions or claims outstanding or pending as of December 31, 2024 cannot be predicted with certainty, management does not believe that the resolution of these claims, individually or in the aggregate, will have a material adverse effect on the Company’s financial position.
Want the next TUCOWS INC /PA/ commitments disclosure the moment it drops?
Set a Sentinel and we'll alert you the moment TUCOWS INC /PA/'s next filing hits EDGAR. No credit card, your email never gets sold.
Historical Timeline
| Fiscal Year | Filed | |
|---|---|---|
| 2024 | Mar 13, 2025 | Showing above |
| 2019 | Mar 4, 2020 | |
| 2018 | Mar 5, 2019 | |
| 2017 | Mar 6, 2018 | |
| 2015 | Mar 9, 2016 | |
About Commitments Disclosures
Commitments and contingencies disclosures catalog a company's off-balance-sheet obligations and legal exposures — purchase commitments, guarantee arrangements, pending litigation, and regulatory proceedings. These items represent potential future cash outflows that may not appear as liabilities on the balance sheet until they become probable and estimable.
Key signals: litigation reserves and disclosed loss ranges quantify management's estimate of legal exposure, but unquantified "reasonably possible" losses often represent the larger risk. Watch for changes in language around pending cases — shifts from "remote" to "reasonably possible" or increases in estimated loss ranges signal deteriorating outcomes. Unconditional purchase obligations and take-or-pay contracts create fixed cost structures that reduce operational flexibility. Guarantee arrangements for subsidiaries or joint ventures can create cascading obligations. Compare the total commitment schedule against projected free cash flow to assess whether the company can meet its obligations without additional financing.