25. Commitments and contingencies
The Company is subject to certain legal and regulatory proceedings, claims and disputes that arise in the ordinary course of business. The Company will recognize a loss contingency when it is probable a liability has been incurred and the amount of the loss can be reasonably estimated. The Company will disclose any loss contingencies that do not meet both conditions if there is a reasonable possibility that a material loss may be incurred. The Company is currently focusing on managing its working capital and liquidity, which has resulted in delays in making payments to certain vendors. While the amounts due to these vendors are recorded on the Consolidated Balance Sheets, potential legal actions against the Company enforcing payments may result in interest, penalties and/or legal expenses, which may materially affect the Company’s financial position, results of operations or cash flows.
With respect to the specific legal proceedings and claims described below, unless otherwise noted, the amount or range of possible losses is not reasonably estimable. There can be no assurance that the settlement, resolution, or other outcome of one or more matters, including the matters set forth below, during any subsequent reporting period will not have a material adverse effect on the Company’s results of operations or cash flows for that period or on the Company’s financial condition.
In 2024, Jamaica Power Service Company Limited (“JPS”) initiated arbitration proceedings claiming damages of approximately $32,900 for use of alternative fuel due to infrastructure changes required by the Port of Montego Bay where the Company’s Montego Bay terminal was located. The Company asserted force majeure under the contract and has made a counterclaim of approximately $7,200. Arbitration proceedings commenced in the first quarter of 2026, and the Company expects this matter to be resolved in 2026. The Company has accrued for the probable loss as of December 31, 2025.
In 2024, the Company’s contract to provide temporary power services ended as a result of FEMA not renewing the funding of the temporary power project in Puerto Rico. The Company determined that a force majeure event occurred under the lease agreement with the owner of a portion of the turbines used in this temporary power project and accordingly terminated the turbine lease agreement pursuant to the force majeure termination provisions. The lessor subsequently initiated arbitration proceedings seeking damages, fees and costs up to $46,200 as a result of the termination of the lease and alleged damages suffered by certain of the leased units during operation and decommissioning. The Company has a counterclaim of approximately $6,500. Arbitration proceedings have commenced in the first quarter of 2026, and the Company expects this matter to be resolved in 2026. The Company has accrued for the probable loss as of December 31, 2025.
In the first quarter of 2025, Alunorte Alumina do Norte do Brasil S.A. (“Alunorte”) initiated arbitration proceedings at the International Chamber of Commerce (“ICC”). Alunorte claims it is owed damages for alleged delays by the Company to supply gas at the Barcarena Facility and is claiming damages up to BRL 375,700 (approximately $68,200 using exchange rates as of December 31, 2025). The Company believes Alunorte’s claims are without merit and not supported by the contract between the parties, and as a result the Company plans to vigorously defend itself in these proceedings. However, due to the inherent difficulty in predicting the outcome of arbitration, the amount of any probable loss is uncertain. The Company has not accrued any probable losses as of December 31, 2025.
PortoCem is a thermal power plant project originally developed by a third party and later acquired by the Company in 2024. Under its prior ownership, the project was designed for a different location and had executed a CUST, a transmission system usage agreement that establishes rights and obligations for grid connection. As part of the acquisition, the Company redesigned the project to be implemented in Barcarena, Pará, where it could be integrated with the Company’s LNG import and power infrastructure. In 2024, PortoCem submitted a request—approximately two years before the applicable
milestones—to relocate the originally approved transmission connection point, and the Brazilian power regulator, ANEEL, subsequently approved this relocation. The change produced no impact on the tariff paid by consumers for transmission use.
In 2024, despite having approved the new connection point, ANEEL informed PortoCem that certain obligations tied to the original connection point had not been fulfilled and that a penalty of approximately BRL 610,000 ($110,900 using exchange rates in effect as of December 31, 2025) could be imposed under the CUST. PortoCem appealed, and in November 2024, ANEEL suspended imposition of any penalty, which remains in force and prevents enforcement until the ANEEL Board of Directors issues a final decision. During the fourth quarter of 2025, the matter was scheduled to be examined by ANEEL’s Board of Directors, however, as of the date of the issuance of these financial statements, ANEEL’s Board has not rendered a final decision and the outcome remains uncertain. The Company has not accrued any probable losses as of December 31, 2025.
If the Company were to receive an unfavorable decision, the matter may still be challenged in the Brazilian courts. Finally, the Company believes that if any penalty is ultimately imposed and enforced by the courts, the original third-party developer of the project is required to indemnify the Company for any losses incurred related to the relocation of the project because the relocation request resulting in any penalty was submitted before the closing of the sale of PortoCem to the Company, thus such regulatory request was filed when PortoCem was controlled by its prior owner. These matters are not expected to be resolved in the near term, and as such, the Company’s ability to collect amounts due under the indemnification obligation are subject to the future condition of the prior owner, which is uncertain. There can be no assurance that the prior owner will have sufficient solvency and financial condition to honor an indemnification obligation.
In the third quarter of 2025, a contractor under an Engineering, Procurement and Construction (“EPC”) contract initiated arbitration proceedings. The contractor claims that it is owed damages for alleged breach of the EPC contract for the construction of the Barcarena Power Plant by the Company and is claiming damages up to approximately BRL 501,000 ($91,000 using exchange rates as of December 31, 2025). The Company has a counterclaim of approximately BRL 400,100 ($72,700 using exchange rates as of December 31, 2025). The Company believes the plaintiff’s claims are without merit and not supported by the contract between the parties, and as a result the Company plans to vigorously defend itself in these proceedings. However, due to the inherent difficulty in predicting the outcome of arbitration, the amount of any probable loss is uncertain. The Company has not accrued any probable losses as of December 31, 2025.
Various local communities and organizations in Brazil have made claims against the Company seeking compensation for alleged damages arising out of the Company’s operations in Brazil. The plaintiffs are claiming damages up to BRL 616,300 (approximately $112,000 using exchange rates as of December 31, 2025). The Company believes the plaintiffs’ claims are without merit, and as a result the Company plans to vigorously defend itself in these proceedings. However, due to the inherent difficulty in predicting the outcome of arbitration, the amount of any probable loss is uncertain. The Company has not accrued any probable losses as of December 31, 2025.
On September 17, 2024, plaintiff Mikolaj Bojdol filed a putative class action lawsuit in the U.S. District Court for the Southern District of New York against the Company and certain officers alleging violations of Sections 10(b) and 20(a) of the Securities and Exchange Act of 1934 and certain rules promulgated thereunder relating to statements concerning the Company’s FLNG project in Altamira, Mexico. On November 1, 2024, plaintiff Taylor Anderson filed a similar class action lawsuit also in the U.S. District Court for the Southern District of New York. The cases were consolidated and a lead plaintiff was appointed on December 17, 2024. The lead plaintiff filed an amended complaint on February 18, 2025 asserting claims on behalf of persons and entities that purchased the Company’s securities between September 20, 2022 and August 8, 2024 and seeks compensatory damages, interest, fees, and costs. On February 19, 2026, the Court denied the defendants’ motion to dismiss. While the Company believes the claims are without merit, and plans to vigorously defend itself in these proceedings, a loss is reasonably possible. A liability has not been recognized as of December 31, 2025, since the Company is unable to predict the outcome given the significant uncertainty with regard to whether such matters will proceed to trial, among other uncertainties. Therefore, the Company is not in a position to assess the likely outcome, and therefore unable to estimate of the range of possible loss.
Changes in regulatory or other governmental policies may affect the delivery of LNG to our terminals, including our San Juan terminal, which may have an adverse effect on the Company’s financial position, results of operations or cash flows.
As of December 31, 2025 and 2024, the Company has accrued a liability of $52,421 and $0, respectively. The liability as of December 31, 2025 represents management’s estimate of probable losses for certain legal matters.